ADD STONE like stone paint painting construction complete process description
Like stone Paint Spray construction method
- Wall disposal before coating - clean and flatten smooth the wall
- Masking and protection: cover the unapplied parts with Cloth-Masker and masking tape to avoid paint contamination
- Primer applied, infiltrated, attached to the base
- Elastic colored coating applied to cover the base color, set off the main material texture, and cover the fine cracks
- Like stone paint texture main material coating spray construction: cross spray twice to create granite texture color
- Sealer topcoat: Lastly covered with transparent protective topcoat, resistant to dirt and easy to clean, extend the life of like stone paint
- Remove the protection after completion, check the details and clean up the waste
Step:1 Clean flatten the surface
- Clean the wall surface, dirt, debris, and clean the wall surface, do not leave mud, dirt, grease, to avoid affecting the adhesion of the primer
- Cut out the protrusions and metal objects
Sept:2 Flatten the surface
- Use the paste filler to level the wall so that the wall is not recessed and uneven
- If the wall has cracks, broken corners, it needs to be filled with cement and remove the sludge.
Step:3 Apply protection material to all the areas not intended to be coated.
Please cover the area that is not sprayed with protective material.
Step:4 Coat a primer coat
- Primer is the most important material to connect with the base surface. Choose the appropriate primer for different interfaces.
- You can choose to roll or spray the primer on the wall
- Primer:1 layer
- Preparation: no water added
- #1.5 nozzle
- Drying Time: 2~3hr (Depending on climate, temperature and humidity will vary)
Step:5 Coat a elastic coat
- The function of the elastic coating is to increase the ductility and the saturation of the main material color.
- You can choose to roll or spray the primer on the wall
- Elastic:1 layer
- Preparation: 5% of water
- #1.5 nozzle
- Drying Time: 2~3hr (Depending on climate, temperature and humidity will vary)
Step:6 Coat main material 1~2 layers
- Highly simulated granite coatings let you create your own granite
- Please spray the main material with air gun
- Main Material: 2 layers.
- Please put the cap on the first layer. and take off cap on second layer.
- Preparation: no water added
- #2.5 nozzle
- Drying Time: 3~4hr (Depending on climate, temperature and humidity will vary)
Step:7 Coat a sealer
- The main function of the topcoat is to protect the stone system.
- Topcoat with self-cleaning, weather-assistant , water-assistant etc. feathers
- You can choose to roll or spray the primer on the wall
- Sealer:2 layer
- Preparation: 50% of water
- #1.5 nozzle
- Drying Time: 2~3hr (Depending on climate, temperature and humidity will vary)
Finish: Granite Texture Coating
Drying Time:Single coat at standard thickness (28℃、50%RH)
- Touch Dry: 2 hours
- Hard Dry: 2 days
Construction Notes
- Before spraying, it is necessary to clean the wall surface and remove the protrusions and fill the slits to ensure that the wall surface is clean .
- During construction, the moisture content of the surface material should be below 10%, the pH value is below 10, and the temperature is above 5 °C.
- Different primers are required depending on the surface material.
- Please cover the area that is not sprayed with protective material.
- Each layer must be sprayed after the previous layer has been sufficiently dried.
- Do not apply in humid air or on rainy days.
- Do not mix with any solvents or paint or water to avoid deterioration.
- Do not stir with a high speed mixer.
- The transportation and storage of materials should be safe, avoiding sunshine, high temperatures and contamination.
Click to see more construction details teaching